PACKAGE PLANTS AND TURN KEY
CONSTRUCTION PROJECTS
(DESIGN + CONSTRUCTION + EQUIPMENT
SUPPLY)
|
|
|
|
|
|
Name of Project
|
:
|
HAMİTABAD NATURAL GAS POWER PLANT PACKAGE DOMESTIC WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Turkish Electricity Board
|
|
Design Population
|
:
|
1000
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
TUSAN HOTEL (KUŞADASI) WASTEWATER
TREATMENT PLANT
|
|
Employer
|
:
|
Tusan Co.
|
|
Design Population
|
:
|
500
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
METEOR
HOLIDAY RESORT (BODRUM-AKYARLAR) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
S.S. Dinlenme Evleri
Yapı Koop.
|
|
Design Population
|
:
|
1000
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
GÜMBET
BAY (BODRUM) WASTEWATER TREATMENT PLANT DESIGN AND ELECTROMECHANICAL
EQUIPMENT SUPPLY
|
|
Employer
|
:
|
Ero Construction Co.
|
|
Design Population
|
:
|
3000
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ELBİSTAN
SUGAR FACTORY COMPLEX
|
|
Employer
|
:
|
Turkish Sugar Industry Co.
|
|
Design Population
|
:
|
2500
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
CENNETEVLER HOLIDAY RESORT
(GÜNDOĞAN-BODRUM) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
ENA Construction Co.
|
|
Design Population
|
:
|
1500
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
SHELL
OIL Co. MEMBERS HOLIDAY RESORT (DATÇA)
|
|
Employer
|
:
|
İnta Co.
|
|
Design Population
|
:
|
200
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
SİVAS
STEEL MILL WASTEWATER TREATMENT PLANT
DESIGN REVISION AND EQUIPMENT SUPPLY
|
|
Employer
|
:
|
General Directorate of Turkish Steel
Ind.
|
|
Design Population
|
:
|
2500
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
GÜNEŞ
HOLIDAY RESORT (DATÇA) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
İnta Cons. Co.
|
|
Design Population
|
:
|
500
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
BAĞLA
HOLIDAY RESORT (BODRUM) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
S.S. Bağla Koop.
|
|
Design Population
|
:
|
2000
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
SEMİRAMİS
HOLIDAY VILLAGE (GÜLLÜK-BODRUM)
WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
SMT
+ H.J. STAGIER & PARTNERS
|
|
Design Population
|
:
|
3100
|
|
Treatment Process
|
:
|
Flow equalization + Extended aeration + Chlorination + Pressurised
Sand Filter + 800m3 storage tank
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
MİKES
MICROWAVE ELECTRONIC PLANT (ANKARA) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Metiş Construction Co.
|
|
Design Population
|
:
|
200
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
PALMA
HOLIDAY RESORT (MERSİN) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Nizam Architects
|
|
Design Population
|
:
|
1500
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ESENBOĞA
AIRPORT (ANKARA) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Ministry of Transportations
|
|
Design Population
|
:
|
21.000 (50 Lt/s)
|
|
Treatment Process
|
:
|
Low Rate Activated Sludge + Chlorination + Aerobic Sludge
Stabilisation + Sludge Dewat.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KAMELYA HOLIDAY RESORT (SİDE)
WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Kamelya III Yapı Kooperatifi
|
|
Design Population
|
:
|
1000
|
|
Treatment Process
|
:
|
Flow Equalisation + Activated Sludge
+ Chlorination + Pressurised Sand Filters
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
TATVAN (BİTLİS)
WASTEWATER TREATMENT PLANT ELECTROMECHANICAL EQUIPMENT SUPPLY
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces) + İÇTAŞ Co.
|
|
Design Population
|
:
|
93.520
|
|
Treatment Process
|
:
|
-
|
|
Electromechanical Equipment
|
:
|
- 37 kW Surface Aerator 8 nos.
- 18.5 kW Surface Aerator 4 nos.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
NİZİP
(GAZİANTEP) WASTEWATER TREATMENT PLANT ELECTROMECHANICAL EQUIPMENT SUPPLY
|
|
Employer
|
:
|
EDA Construction + İller Bankası
|
|
Design Population
|
:
|
200.000
|
|
Treatment Process
|
:
|
-
|
|
Electromechanical Equipment
|
:
|
- 37 kW Surface Aerator 6 nos.
- 18.5 kW Surface Aerator 3 nos.
- 26m diameter Primary Sed.Tank scraper bridges (2 no.s)
- 26m diameter Secondary Sed.Tank scraper bridges (3 no.s)
- Mechanically cleaned bar screens
(2 no.s.)
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
MİLPA
HOLIDAY VILLAGE WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Milliyet Pazarlama
|
|
Design Population
|
:
|
1800
|
|
Treatment Process
|
:
|
Equalization + Extended Aeration
+Chlorination + Pressurised Sand Filter
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ABANT
İZZET BAYSAL UNIVERSITY WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
İzzet Baysal University + AKAY Const.
|
|
Design Population
|
:
|
4000
|
|
Treatment Process
|
:
|
Extended Aeration + Pressurised Sand Filter
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
BOTAŞ
YAPRACIK WATER TREATMENT AND SOFTENING SYSTEMS
|
|
Employer
|
:
|
BOTAŞ + CNFA Cons.
|
|
Design Capacity
|
:
|
720 m3/day
|
|
Treatment Process
|
:
|
Hydroantracit Filter + Water Softening with Ion
Exchange
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
TSCHERNORETSCHJE
(SAMARA REGION-RUSSIA) MILITARY HOUSING PROJECT, CONSTRUCTION OF SPORTS
COMPLEX BUILDING
|
|
Employer
|
:
|
J.V. HMB Tekfen
|
|
Contract Duration
|
:
|
9 months
|
|
Specification
|
:
|
Concrete and steel composite
structure with 7000 m2 closed area, a prestigious building.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
TSCHERNORETSCHJE
(SAMARA REGION-RUSSIA) CONSTRUCTION OF CLUB HOUSE
|
|
Employer
|
:
|
J.V. HMB Tekfen
|
|
Contract Duration
|
:
|
9 months
|
|
Specification
|
:
|
Concrete structure with 6 000 m2 closed area,a prestigious building.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
TSCHERNORETSCHJE
(SAMARA REGION-RUSSIA) MILITARY HOUSING PROJECT, CONSTRUCTION OF SERVICE,
LAUNDRY AND BAKERY BUILDINGS
|
|
Employer
|
:
|
J.V. HMB Tekfen
|
|
Contract Duration
|
:
|
9 months
|
|
Specification
|
:
|
Three Concrete and steel composite structures with 5500 m2 closed
area.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
JEGORLIKSKAYA (ROSTOV REGION-RUSSIA)
MILITARY HOUSING PROJECT CONSTRUCTION OF DOMESTIC WASTEWATER TREATMENT
PLANT
|
|
Employer
|
:
|
J.V. GABEG-ENKA
|
|
Design Capacity
|
:
|
1500 m3/day
|
|
Treatment Process
|
:
|
Nitrification-Denitrification +
Chemical phosphorus removal + Pressurised filtration + Chlorination +
Sludge Thickener + Sludge Drying Beds
|
|
Contract Duration
|
:
|
7 months
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
JEGORLIKSKAYA (ROSTOV REGION-RUSSIA)
MILITARY HOUSING PROJECT CONSTRUCTION OF KINDERGARDEN
|
|
Employer
|
:
|
J.V. GABEG-ENKA
|
|
Contract Duration
|
:
|
7 months
|
|
Specifications
|
:
|
Concrete structure with 3000 m2 closed
area, a prestigious building.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ŞİRİNGÖLKÖY
(ANKARA) VILLAGE WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Şiringölköy + Artek
Co.
|
|
Design Population
|
:
|
650
|
|
Treatment Process
|
:
|
Extended aeration + Chlorination +
Pressurized Sand Filter +Water Pressurizing System.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
AKÇABÜK
HOLIDAY RESORT (BODRUM) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
AKYAP CO.
|
|
Design Population
|
:
|
4500
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
OYAK -
RENAULT AUTOMOBILE MANUFACTURING PLANT (BURSA) INDUSTRIAL WASTEWATER
TREATMENT PLANT ELECTROMECHANICAL
EQUIPMENT SUPPLY
|
|
Employer
|
:
|
HIDRO - OTV (France)
|
|
Design Capacity
|
:
|
-
|
|
Treatment Process
|
:
|
-
|
|
Electromechanical Equipment
|
:
|
- Primary sed. Tank scraper +
thickener bridge
- Secondary sed. Tank scraper bridge
- DAF equipment
- Mechanically cleaned bar screen
- Basket type manual screens
- Bins (containers) for dewatered
sludges
- Bins for screenings
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
YEŞİLYURTLULAR
HOLİDAY RESORT (BODRUM) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Yeşilyurtlular Koop.
|
|
Design Population
|
:
|
340
|
|
Treatment Process
|
:
|
Extended aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
DALYAN HOLIDAY RESORT(BODRUM) WASTEWATER
TREATMENT PLANT
|
|
Employer
|
:
|
Alfa Cons. Ltd.
|
|
Design Population
|
:
|
400
|
|
Treatment Process
|
:
|
Extended aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
İZMİT
WATER TREATMENT PLANT, CONSTRUCTION OF CHEMICAL ,CHLORINATION &
GENERATOR BUILDINGS, SLUDGE THICKENING TANK
|
|
Employer
|
:
|
Güriş Construction Co.
|
|
Design Population
|
:
|
-
|
|
Treatment Process
|
:
|
-
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
BODRUM -
MİLAS AIRPORT WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Simge Cons. Co.
|
|
Design Capacity
|
:
|
1000 m3/day
|
|
Treatment Process
|
:
|
Extended aeration +
Nitrification-Denitrification+ Chemical Phosphorus treatment.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
AKSARAY WATER TREATMENT PLANT
|
|
Employer
|
:
|
Municipality of Aksaray
|
|
Design Population
|
:
|
60,000 m3/day
|
|
Treatment Process
|
:
|
Cascade aeration + Upward flow
sludge blanket type clarifiers + rapid sand filters + chlorination.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
BURSA
AIRPORT WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Tema Construction Co.
|
|
Design Population
|
:
|
650 m3/day
|
|
Treatment Process
|
:
|
Extended aeration activated sludge
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
BEYŞEHİR
WASTEWATER TREATMENT PLANT
(Mechanical and electrical equipment supply, manufacture and installation)
|
|
Employer
|
:
|
Bank of Proviences
+ Mesut Yılmaz Cons. Co.
|
|
Design Population
|
:
|
-
|
|
Treatment Process
|
:
|
Activated sludge
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
BASRAH
(IRAQ) WASTEWATER TREATMENT PLANT
SUPPLY OF ELECTROMECHANICAL EQUIPMENT
|
|
Employer
|
:
|
Ministry of Municipalities and Works (IRAQ) + YEDAŞ Co.
|
|
Design Population
|
:
|
700000
|
|
Treatment Process
|
:
|
Activated sludge
|
|
Equipment Capacities
|
:
|
- Primary Sed Scrapes Ø40m 2 no.
- Seconds Sed Scrapes Ø40m 12
no.
- Surface aerators 37Kw 32 no.
- Gravity Thickeners Ø24m 3 no.
- Adjustable Level Weirs L=4m 16
no.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ANTS
HEADQUARTERS PACKAGE WASTEWATER
TREATMENT PLANT
|
|
Employer
|
:
|
ANTS Co.
|
|
Design Population
|
:
|
100
|
|
Treatment Process
|
:
|
SBR Type Biological Treatment
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KURTALAN
CEMENT FACTORY PACKAGE WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Limak Construction
Co.
|
|
Design Population
|
:
|
500
|
|
Treatment Process
|
:
|
SBR Type Biological Treatment
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ANACONDA
AIR BASE (BALAD/IRAQ) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
US Army + Yüksel Co.
|
|
Design Population
|
:
|
20.000 P.E.
|
|
Treatment Process
|
:
|
Inlet pump station + equalization
tanks + activated sludge + aerobic sludge digestion + disinfection + sludge
dewatering.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
JAF
FACILITIES (JORDAN) PACKAGE PLANT FOR GREYWATER TREATMENT and REUSE
|
|
Employer
|
:
|
Jordan Armed Forces + Aysel Co.
|
|
Design Capacity
|
:
|
30 m3/hr
|
|
Treatment Process
|
:
|
Coagulation / flocculation + sedimentation
+ dissolved air flotation + sand filtration + chlorination
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
SULEIMANI
UNIVERSITY (IRAQ) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
FDC-TEPE Joint Venture
|
|
Design Population
|
:
|
10.000 P.E.
|
|
Treatment Process
|
:
|
Activated sludge + aerobic sludge
digestion + disinfection + sludge dewatering.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ÇATAK (VAN) MUNICIPAL SOLID WASTE COMPOSTING
PLANT
|
|
Employer
|
:
|
Surkal +
Municipality of Çatak
|
|
Process
|
:
|
Sorting +
Shredding + Rotating Drum for Mixing and Aerating + Windrows
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
GÜRİŞ CO. CONSTRUCTION CAMP (TRIPOLI/LIBYA)
PACKAGE WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Güriş Co.
|
|
Design Population
|
:
|
300
|
|
Treatment Process
|
:
|
SBR Type Biological Treatment
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KOYA (KUYSANJAQ/IRAQ) WATER SUPPLY PROJECT
|
|
Employer
|
:
|
Ministry of Municipalities
|
|
Design Capacity
|
:
|
30.000 m³/day
|
|
Treatment Process
|
:
|
Cascade aeration + Rapid Mixing +
Flocculators + Radial flow Clarifiers + rapid sand filters + chlorination.
|
|
Plant Units
|
:
|
- Intake structure + Intake pump
station (1200 m³/hr Hm=270m)
- Low lift pump station (1200
m³/hr Hm=220m)
- Heybesultan pump station ( 300
m³/hr Hm=60m)
- Heybesultan Reservoir (10000 m³)
- Hamamoc Reservoir (5000 m³)
- Sheidan Reservoir (5000 m³)
- 30km DN600 PN40 Ductile Iron Pipe
- 10km DN300 PN25 Ductile Iron Pipe
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ÖZALTIN CO. CONSTRUCTION CAMP (DARNAH/LIBYA)
PACKAGE WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Özaltın Co.
|
|
Design Population
|
:
|
600
|
|
Treatment Process
|
:
|
SBR Type Biological Treatment
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KOYA (KUYSANJAQ/IRAQ) WATER SUPPLY PROJECT
PLANT OPERATION and MAINTENANCE
|
|
Employer
|
:
|
Ministry of Municipalities
|
|
Design Capacity
|
:
|
30.000 m³/day
|
|
Treatment Process
|
:
|
Cascade aeration + Rapid Mixing +
Flocculators + Radial flow Clarifiers + rapid sand filters + chlorination.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
PIKARON CO. CONSTRUCTION CAMP (MOUSUL/IRAQ)
PACKAGE WATER TREATMENT PLANT
|
|
Employer
|
:
|
Pikaron Co.
|
|
Design Population
|
:
|
300
|
|
Treatment Process
|
:
|
Rapid mix + flocculation + lamella
sedimentation + sand filtration + chlorination
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ENGINEERING
and CONSULTANCY PROJECTS
|
|
|
|
|
|
Name of Project
|
:
|
JUBAIL (S.ARABIA) COST GUARD FACILITIES WASTEWATER TREATMENT PLANT INFRASTRUCTURE
PROJECT
|
|
Employer
|
:
|
Gulf Trading and Agriculture Co.
|
|
Design Population
|
:
|
100
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ALİAĞA (İZMİR) WATER TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
300.000
|
|
Treatment Process
|
:
|
1.Phase: Aeration + Rapid Sand Filter + Slow Sand Filter + Chlorination
2.Phase: Aeration + Coagulation-Floculation - Sedimentation + Rapid Sand Filter +
Chlorination
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ZLITEN (LIBYA) RESIDENTIAL AREA INFRASTRUCTURE
|
|
Employer
|
:
|
Özdemir Cons. Co.
|
|
Design Population
|
:
|
2.500
|
|
Treatment Process
|
:
|
|
|
Scope of Work
|
:
|
Road, Water, Sewerage, Treatment
|
|
|
|
|
|
Name of Project
|
:
|
TİRE
(İZMİR) SEWERAGE PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
70.000
|
|
Treatment Process
|
:
|
|
|
Length of Network
|
:
|
150 km
|
|
Main interceptor
|
:
|
2.816 m Ø 700
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
PRELIMINARY
ENGINEERING DESIGNS FOR DOMESTIC WASTEWATER TREATMENT PLANT OF ÇAYIRHAN
THERMIC POWER PLANT
|
|
Employer
|
:
|
Günal Cons. Co.
|
|
Design Population
|
:
|
1.700
|
|
Treatment Process
|
:
|
Power Plant : Extended Aeration
Residences : Imhof
Tank + Biodisc
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ESKİKÖY
(ORDU) DIVERSION WEIR & WATER TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
10.000
|
|
Treatment Process
|
:
|
Plain Sedimentation + Slow Sand Filters + Chlorination
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KOZAN (ADANA)
WASTEWATER TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
145.528
|
|
Treatment Process
|
:
|
1.Phase: Anaerobic + Facultative
2.Phase: Aerobic lagoon + Facultative
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
DÜZiÇi
(ADANA) SEWERAGE PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
111.000
|
|
Treatment Process
|
:
|
|
|
Length of Network
|
:
|
300 km
|
|
Main Interceptor
|
:
|
2.800 m
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ŞEFAATLi (YOZGAT) SEWERAGE PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
40.000
|
|
Treatment Process
|
:
|
|
|
Length of Network
|
:
|
64 km
|
|
Main Interceptor
|
:
|
1.600 m
|
|
Pumping Station
|
:
|
2 nos. (Hm=25 m , Q=200 Lt/sn)
|
|
Main Interceptor
|
:
|
1.600 m
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
TERME (SAMSUN) WASTEWATER TREATMENT
PLANT PROJECT
|
|
Employer
|
:
|
Özkar Co. + İller Bankası
|
|
Design Population
|
:
|
43.000
|
|
Treatment Process
|
:
|
1.Phase: Facultative Stab. Ponds
2.Phase: Aerobic + Facultative
ponds
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
MKE
KIRIKKALE WEAPON FACTORY INDUSTRIAL WASTEWATER TREATMENT PLANT PRELIMINARY
DESIGNS
|
|
Employer
|
:
|
BMB Co.
|
|
Design Population
|
:
|
|
|
Treatment Process
|
:
|
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ANTAKYA WASTEWATER TREATMENT PLANT PRELIMINARY DESIGNS
|
|
Employer
|
:
|
Nurol Construction Co.
|
|
Design Population
|
:
|
214.000
|
|
Treatment Process
|
:
|
High Rate Trickling Filter + Aerobic Sludge Stablization
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ÇUKUROVA METROPOLITAN REGION URBAN DEVELOPMENT PROJECT TARSUS URBAN
EXPANSION AREA ON AND OFF SITE INFRASTRUCTURE PHASE 1, 2, AND 3 CONSULTANCY
AND CONSTRUCTION MANAGEMENT SERVICES
|
|
Employer
|
:
|
Asfen Construction Co.
|
|
Design Population
|
:
|
|
|
Treatment Process
|
:
|
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KARAPÜRÇEK (BALIKESİR) POTABLE WATER TREATMENT PLANT
PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
24.000
|
|
Treatment Process
|
:
|
Plain Sedimentation + Slow Sand Filters + Chlorination
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KORGAN(ORDU) POTABLE WATER TREATMENT
PLANT PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
25.000
|
|
Treatment Process
|
:
|
Plain Sedimentation + Slow Sand Filters + Chlorination
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
NEVŞEHİR RAKI FACTORY INDUSTRIAL WASTEWATER TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
Nurol Co.
|
|
Design Population
|
:
|
80.000
|
|
Treatment Process
|
:
|
Flow Equalization + Anaerobic Treatment + High Rate + Activated
Sludge + Low Rate Activated Sludge
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
SAFMAYA
YEAST FACTORY (AMASYA) INDUSTRIAL WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Garipoğlu Co.
|
|
Design Population
|
:
|
200.000
|
|
Treatment Process
|
:
|
1.Phase: Two stage Activated Sludge +
Aerobic Sludge Stabilisation + Sludge Thickening (Completed)
2.Phase: Addition of equalization
tank and intermediate settling units, anaerobic reactor. (Abolished)
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
F.N.S.S. ARMOURED COMBAT VEHICLE (GÖLBAŞI/ANKARA)
WATER QUALITY CONTROL AND CONSULTANCY SERVICES
|
|
Employer
|
:
|
FMC - Nurol Co.
|
|
Design Population
|
:
|
|
|
Treatment Process
|
:
|
|
|
Scope of Work
|
:
|
Geological and hydrological studies of the region, laboratory tests
on the samples from deep wells. Recommendation for the disinfection
system.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
YOZGAT ORGANISED INDUSTRIAL
ZONE WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Ministry of Industry
|
|
Design Population
|
:
|
|
|
Treatment Process
|
:
|
Low Rate Activated Sludge + Aerobic
Sludge + Stab. + Sludge Digestion + Belt Filter
|
|
Design Discharge
|
:
|
100 Lt/s
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ÇERKEZKÖY (TEKİRDAĞ) WASTEWATER TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
250.000
|
|
Treatment Process
|
:
|
Activated Sludge
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
NALLIHAN (ANKARA) SEWERAGE PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
50.000
|
|
Treatment Process
|
:
|
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ABANT
İZZET BAYSAL UNIVERSITY BOLU CAMPUS WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Izzet Baysal University
|
|
Design Population
|
:
|
4.000
|
|
Treatment Process
|
:
|
Extended Aeration
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
DÖRTYOL
(ADANA) WASTEWATER TREATMENT PLANT, FEASIBILITY STUDIES
|
|
Employer
|
:
|
Municipality of Dörtyol
|
|
Design Population
|
:
|
140.000 PE (for first stage)
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge +
Nitrification + Denitrification Process + Biological Phosphorus removal
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KIRIKHAN (HATAY) WASTEWATER
TREATMENT PLANT, FEASIBILITY STUDIES
|
|
Employer
|
:
|
Municipality of Kırıkhan
|
|
Design Population
|
:
|
125.000 PE (for first stage)
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge +
Nitrification + Denitrification Process + Biological Phosphorus removal
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
TÜRKELLİ (TRABZON) WATER TREATMENT
PLANT PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces)
|
|
Design Population
|
:
|
11.000
|
|
Treatment Process
|
:
|
Plain Sedimentation + Slow Sand
Filters + Chlorination
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ADAPAZARI
WASTEWATER TREATMENT PLANT, MAIN COLLECTOR AND REHABILITATION OF ÇARK CREEK
CONSULTANCY and CONSTRUCTION SUPERVISION SERVICES
|
|
Employer
|
:
|
Municipality of Adapazarı – Erge Ltd. Şti.
|
|
Design Population
|
:
|
1.650.000 PE
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge +
Nitrification + Denitrification Process. 4 km Ø2400 RC Main Collector, 7.4 kmRehabilitation of Çark Creek.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
EDİRNE
WASTEWATER TREATMENT PLANT, FEASIBILITY STUDIES
|
|
Employer
|
:
|
Municipality of Edirne
|
|
Design Population
|
:
|
285.000 PE
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge +
Nitrification + Denitrification Process + Biological Phosphorus removal
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KONYA
WASTEWATER TREATMENT PLANT, FEASIBILITY STUDIES
|
|
Employer
|
:
|
Municipality of Konya
|
|
Design Population
|
:
|
650.000 PE (for first stage)
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge +
Nitrification + Denitrification Process + Biological Phosphorus removal
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
MERCEDES-BENZ(AKSARAY-TURKEY)
INDUSTRIAL AND DOMESTIC WASTEWATER TREATMENT PLANT FEASIBILITY PROJECT
|
|
Employer
|
:
|
|
|
Design Population
|
:
|
600m3/day
ind.ww + 400 m3/day domestic.
|
|
Treatment Process
|
:
|
Equalization + Chemical treatment
processes + Biological traetment processes
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
AYTAÇ
POULTRY PLANT INDUSTRIAL WASTEWATER TREATMENT PLANT FEASIBILITY PROJECT
|
|
Employer
|
:
|
|
|
Design Population
|
:
|
2500m3/day
|
|
Treatment Process
|
:
|
Equalization + Chemical treatment
processes (flocculation+settling+DAF)+ Biological
traetment processes
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ÇINARCIK
(YALOVA) WASTEWATER TREATMENT PLANT
AND SEA OUTFALL PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces) + Özbek
Co.
|
|
Design Population
|
:
|
230.000 P.E
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge +
Nitrification + Denitrification Process
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ESENKÖY
(YALOVA) WASTEWATER TREATMENT PLANT AND SEA OUTFALL PROJECT
|
|
Employer
|
:
|
İller Bankası (Bank of Provinces) + Özbek Co.
|
|
Design Population
|
:
|
47.000 P.E
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge +
Nitrification + Denitrification Process
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
AKYAKA –
GÖKOVA (MUĞLA) WASTEWATER TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
Ministry of Environment, Specially Protected Areas
|
|
Design Population
|
:
|
30.000 P.E.
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge + Nitrification +
Denitrification Process + Phosphorus removal + Disinfection + Sludge
dewatering
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
PAMUKKALE
(DENİZLİ) WASTEWATER TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
Ministry of Environment, Specially
Protected Areas
|
|
Design Population
|
:
|
26.300 P.E.
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge + Nitrification +
Denitrification Process + Phosphorus removal + Disinfection + Sludge dewatering
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
AKKÖY
(DENİZLİ) WASTEWATER TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
Ministry of Environment, Specially Protected Areas
|
|
Design Population
|
:
|
49.400 P.E.
|
|
Treatment Process
|
:
|
Extended Aeration Activated Sludge + Nitrification +
Denitrification Process + Phosphorus removal + Disinfection + Sludge dewatering
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
GÖCEK (MUĞLA) WASTEWATER TREATMENT
PLANT
|
|
Employer
|
:
|
Ministry of Environment, Specially Protected Areas
|
|
Design Population
|
:
|
12000 PE
|
|
Treatment Process
|
:
|
Activated sludge (Sequencing
Batch Reactor)
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
AKSARAY WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
Ministry of Environment
|
|
Design Population
|
:
|
250.000 P.E.
|
|
Treatment Process
|
:
|
Nitrification + Denitrification +
Biological Phosphorus Removal + Sludege
Dewatering
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
BASRAH (IRAQ) WASTEWATER TREATMENT
PLANT DESIGN REVISIONS
|
|
Employer
|
:
|
Ministry of Municipalities and Works
(IRAQ) + YEDAŞ Co.
|
|
Design Population
|
:
|
700.000 P.E.
|
|
Treatment Process
|
:
|
Activated Sludge + Anaerobic Sludge
Digestion + Gas Store Tanks, Sludge
Dewatering
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
KHOST
ANABRIGADE (AFGANISTAN) WASTEWATER TREATMENT PLANT
|
|
Employer
|
:
|
U.S. Army + Yüksel Co.
|
|
Design Population
|
:
|
3000 P.E.
|
|
Treatment Process
|
:
|
Aerated lagoons
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ILICA
(ANTALYA) WATER and SEWERAGE PROJECT CONSULTANCY and CONSTRUCTION SUPERVISION SERVICE (Funded by the
World Bank)
|
|
Employer
|
:
|
Ilıca Municipality
|
|
Design Population
|
:
|
12.112 m
HDPE water pipes,
18.269m
HDPE sanitary sewage pipes,
7.236m
Concrete stormwater pipes,
1 no.
sewerage pump station,
277m forced main.
|
|
Treatment Process
|
:
|
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
BURSA
WASTEWATER TREATMENT PLANTS CONSULTANCY and CONSTRUCTION SUPERVISION SERVICE
|
|
Employer
|
:
|
Bursa Water and Sewerage Authority + Yüksel
Co.
|
|
Design Population
|
:
|
- East Treatment Plant : 1.550.000 PE
- West Treatment Plant : 650.000 PE
- Leachete
Treatment Plant leachate from
- 25 million tons of landfill.
|
|
Treatment Process
|
:
|
|
|
Ekotek Scape
|
:
|
40 man mounths
of experts service for study and approval of process and mechanical
designs.
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ELBİSTAN WASTEWATER TREATMENT PLANT
PROJECT
|
|
Employer
|
:
|
İller Bankası
|
|
Design Population
|
:
|
133.000 PE
|
|
Treatment Process
|
:
|
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
HASANOĞLAN
WASTEWATER TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
ASKİ (Ankara Water and Sewerage Authority) + Yüksel
Co.
|
|
Design Population
|
:
|
100.000 PE
|
|
Treatment Process
|
:
|
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
ANKARA CREEK WATER QUALITY
IMPROWEMENT PROJECT
|
|
Employer
|
:
|
ASKİ (Ankara Water and Sewerage Authority) + Yüksel
Co.
|
|
Design Population
|
:
|
6 m3/sec
|
|
Treatment Process
|
:
|
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
SİLOPİ POWER PLANT RAW WATER
TREATMENT PLANT PROJECT
|
|
Employer
|
:
|
PARK HOLDİNG + Eser Co.
|
|
Design Population
|
:
|
630 m3/hr
|
|
Treatment Process
|
:
|
|
|
|
|
|
|
|
|
|
|
Name of Project
|
:
|
AL QARABULI (LIBYA) WASTEWATER
TREATMENT PLANT
|
|
Employer
|
:
|
TABAK Co.
|
|
Design Population
|
:
|
2000 m3/day
|
|
Treatment Process
|
:
|
|